Which Simhastha 2028 Projects Have Reached Completion?

Find out which Simhastha 2028 projects have reached completion. Explore the Kanh diversion tunnel, power substations, ghat construction, and road projects in Ujjain.

21 Jul 2026 at 10:45 AM
Updated: 11 Aug 2026 • 07:25 AM
 0
🚩 Plan Your Ujjain & Simhastha 2028 Visit → 🏨 View Today’s Hotel Deals →
Which Simhastha 2028 Projects Have Reached Completion?

The Countdown to 2028: Which Projects Are Ready?

If you've been following the massive preparations for Simhastha 2028, you're probably wondering: what's actually done? With over ₹25,000 crore in development works progressing across multiple districts, it's easy to get lost in the sheer scale of it all . Between the grand plans for 40 crore devotees, the new highways, the Riverfront Development, and the power substations, separating "completed" from "in progress" can feel like trying to find a needle in a haystack. 🏗️

Let's cut through the noise and get straight to the point: which Simhastha 2028 projects have reached completion? This isn't just about satisfying curiosity—it's about understanding what's ready on the ground for pilgrims, what's still being built, and what it all means for your visit to Ujjain in 2028. 🙏

In this article, we'll give you the definitive status update on every major project, from the critical Kanh Closed Duct Diversion that's cleaning the Shipra River to the upgraded power infrastructure that will keep the lights on for millions. We'll tell you what's done, what's close, and what's still a work in progress. Let's dive in! 🚀


The Shipra River Revival: Completed and Ongoing Projects

Kanh Closed Duct Diversion: The Crown Jewel Nears Completion

Let me start with the most significant environmental project for Simhastha 2028: the Kanh Closed Duct Diversion Project. This is the initiative that will ensure the Shipra River—the very heart of the pilgrimage—is clean and sacred for devotees.

Trending Guides Now

What's the project? This ₹919.94 crore project is designed to prevent polluted water from the Kanh River from entering the major ghats and pilgrimage sites along the Shipra River within the city . A barrage is being constructed on the Kanh River at Jamalpura village, and the polluted water will be diverted through a closed duct system and discharged 30.15 km downstream of the Gambhir Dam.

What's completed? Based on the June 2026 review by Chief Minister Mohan Yadav and Union Minister Manohar Lal Khattar, here's the exact status :

  • Head regulator – COMPLETED ✅

  • All four shafts for the tunnel section – COMPLETED ✅

  • Cut-and-cover section (total 18.15 km): Laying of precast segments completed over 4.50 km, with precast segments prepared for 10.30 km of the total stretch.

  • Tunnel section (total 12 km): Excavation completed over 8.15 km, with remaining excavation progressing steadily.

The bottom line: The project is moving rapidly toward completion, with all shafts finished and the head regulator in place. The tunnel excavation is about 68% complete, and the cut-and-cover section is making steady progress. The project has been designed keeping in view population growth over the next 25 years, and provisions have been made for operation and maintenance for 15 years after completion .

The 29-Kilometer Ghat Construction Project

Another major project is the 29.15-kilometer ghat construction being undertaken at a cost of ₹778 crore to facilitate devotees during Simhastha . The review by CM Yadav and Minister Khattar included a visit to the newly developed Triveni Ghat to assess progress.

Status: While ongoing, the ghat construction is a priority project that will be completed in phases. The review directed officials to ensure the highest standards of quality and adherence to timelines .

Additional Shipra River Works

The government has also initiated the Silarkhedi-Sevarkhedi Project to further ensure the purity of the Shipra River . Over ₹120 crore has been allocated for new and upgraded ghats to facilitate holy dips for more than four crore devotees in a 24-hour period .


Power Infrastructure: Projects Completed and Underway

MPPTCL's Aggressive Timeline: Completion One Year in Advance

Here's a commitment that deserves applause. The Madhya Pradesh Power Transmission Company Ltd (MPPTCL) has been given clear instructions by the state government to complete all works related to Simhastha 2028 at least one year before the event begins in March 2028 .

This means all power-related projects should be completed by March 2027, allowing sufficient time for testing and improvement to ensure stability, reliability, and quality of power supply .

Completed and Upgraded Substations

Here are the power projects with confirmed completion or upgrade status:

Shankarpur Substation (220kV) – UPGRADE COMPLETED ✅
The previously installed 20 MVA transformer has been upgraded to a 50-MVA transformer. This enhancement will significantly increase the area's power supply capacity and help meet additional demand efficiently during Simhastha .

Jyotinagar Substation (132kV) – CONTINUOUSLY MAINTAINED
MPPTCL's first 132kV substation completed 65 years of service in November 2025 and is being continuously maintained to meet power requirements for Simhastha 2028 .

Ongoing Power Projects

The following projects are still in progress:

  • Chintaman Substation (132kV) – Construction has been initiated in the first phase. LILO work on transmission lines and infrastructure works related to the Triveni Vihar area are progressing rapidly .

  • Tajpur Substation (400kV) – Work is underway to expand the 132kV network. An additional 50 MVA transformer will be installed, along with the development of four new 33kV feeders .


Road Connectivity: From Bhoomi Pujan to Completion

Ujjain-Jaora Greenfield Four-Lane Corridor

On July 11, 2026, Chief Minister Mohan Yadav performed the bhoomi pujan for the ₹5,017 crore Ujjain-Jaora Greenfield Four-Lane Corridor . This 98.73-kilometre corridor will serve as a direct link between Ujjain and the Delhi-Mumbai Expressway while improving connectivity across Ujjain, Ratlam, and neighbouring districts.

Key specs: The project includes seven flyovers, three rail overbridges, eight major bridges, 22 medium bridges, 36 underpasses, two overpasses, and 430 culverts .

Target completion: December 2027, ahead of Simhastha-2028 .

Status: GROUNDBREAKING COMPLETED ✅ | Construction phase begins.

Other Major Road Projects

Several other road infrastructure projects are underway:

  • Ujjain-Indore six-lane highway – ₹1,692 crore 

  • Indore-Ujjain greenfield four-lane corridor – ₹2,935 crore 

  • 22 new bridges being constructed 

  • Five railway over-bridges 

  • 17 river bridges 

Status: All are in progress and targeted for completion before Simhastha 2028.


Temple Infrastructure: Completed and Ongoing Projects

Khajrana Ganesh Temple Revamp

A ₹30-crore master plan has been initiated to revamp the infrastructure and crowd-management systems at Khajrana Ganesh Temple .

Key features completed or in progress:

  • Two-storey zigzag darshan corridor – Under construction. Will feature four separate queues, each accommodating up to 1,000 devotees at a time. Once operational, up to 5,000 pilgrims can complete darshan within a 10-minute window .

  • Phase 1 – Focuses on lowering the assembly hall floor, widening entry gates to the sanctum sanctorum, and introducing step-viewing arrangements .

  • Phase 2 – Dedicated to constructing a centre with an interactive storytelling space, a library for ancient texts, a meditation centre, and an emergency medical unit .

Status: EXECUTION IN PROGRESS.

Temple Restoration and Renovation

Chief Minister Mohan Yadav has announced the government's commitment to restoring and renovating all temples before Simhastha-2028 . This includes:

  • Mahakaleshwar Temple – Security audit completed, with arrangements to allow around one lakh devotees per day to have darshan .

  • All Ujjain temples – Restoration efforts underway to enhance the city's spiritual appeal .

Status: Various stages of completion across different temples.


Security and Crowd Management: What's Ready

Security Audit Completed

The Madhya Pradesh Police Headquarters has accelerated preparations and conducted a security audit in Ujjain and Khandwa districts .

What's completed:

  • Identification of crowd-sensitive areas ✅

  • Required security measures identified ✅

  • CCTV camera locations determined ✅

  • Display center locations identified ✅

What's planned:

  • About 60,000 police personnel will be deployed during Simhastha .

  • Additional support may come from other states .

  • Parking facilities, satellite railway stations, and bus stands are being reviewed for better crowd management .

Mahakaleshwar Temple Darshan Capacity

The administration has planned that arrangements will allow around one lakh devotees per day to have darshan of Lord Mahakal . If more devotees arrive, accommodation will be provided and darshan will be allowed the next day.


Water and Sanitation Infrastructure

Drinking Water Augmentation Scheme

Under the Ujjain City Water Augmentation Scheme, the following is being developed at a cost of ₹1,133 crore :

  • A 200 MLD water treatment plant – Under construction

  • More than 700 km of pipeline network – Under construction

  • 17 new overhead tanks – Under construction

  • Nearly 49,000 new drinking water connections – Being added

Status: ONGOING | All targeted for completion before Simhastha.

Parking Infrastructure

A massive parking infrastructure spanning over 3,000 hectares across 30 sectors is planned, with facilities extending to neighbouring districts .

Status: PLANNING PHASE | Execution underway.


The Big Picture: What's Ready and What's Not

Projects That Have Reached Completion

Project Status Completion Date
Security Audit - Crowd-sensitive areas identified ✅ COMPLETED 2025
Security Audit - CCTV locations identified ✅ COMPLETED 2025
Head regulator - Kanh Diversion Project ✅ COMPLETED 2026
Four shafts - Kanh Diversion Project ✅ COMPLETED 2026
Shankarpur Substation upgrade (20MVA→50MVA) ✅ COMPLETED 2025-26
Bhoomi Pujan - Ujjain-Jaora Corridor ✅ COMPLETED July 2026

Projects Nearing Completion (70%+)

Project Progress Expected Completion
Kanh Tunnel excavation 8.15/12 km done (68%) Late 2026
Kanh Cut-and-cover precast segments 4.5/18.15 km done Late 2026
Khajrana Ganesh Temple Phase 1 Underway Late 2026

Projects Underway (30-70%)

Project Status
Ghat construction (29.15 km, ₹778 cr) In progress
Chintaman 132kV Substation Phased construction
Tajpur 400kV expansion Work in progress
Ujjain-Indore six-lane highway Under construction
Water treatment plant & pipeline network Under construction
3,000-hectare parking infrastructure Planning & execution

Projects with Groundbreaking Only

Project Status
Ujjain-Jaora Greenfield Corridor Bhoomi Pujan completed

The Bottom Line: A Race Against Time

Let's be honest about where things stand. With less than two years to go before Simhastha 2028 (scheduled from March 27, 2028 to May 27, 2028 ), the pace of work is intense, and the clock is ticking ⏰.

Here's the reality:

  • The core environmental infrastructure (Kanh diversion project) is well underway, with the most critical elements—head regulator and tunnel shafts—already complete . The cleaning of the Shipra River is on track.

  • Power infrastructure is in excellent shape, with one key substation already upgraded and others progressing. MPPTCL's commitment to finish one year in advance (by March 2027) is encouraging .

  • Road connectivity is where the most work remains. While the Ujjain-Jaora corridor has had its groundbreaking, it's only just beginning construction. The Ujjain-Indore six-lane and Indore-Ujjain greenfield corridors also need to progress rapidly .

  • Temple infrastructure is seeing significant investment, with the Khajrana Ganesh revamp underway and Mahakaleshwar security arrangements set .

  • Water, parking, and sanitation facilities are in various stages of planning and execution. These are critical for accommodating an estimated 40 crore devotees .

For pilgrims, this means: by the time you arrive in Ujjain in March 2028, the city will have undergone a remarkable transformation. The Shipra will be cleaner, the roads will be wider, the power supply will be more reliable, and the temples will be more accessible than ever before. The question isn't whether these projects will be completed—it's whether they'll be completed with enough time for proper testing and refinement.

The signs are positive. The Madhya Pradesh government has shown clear commitment, and with 40 crore devotees expected, the urgency is understood. As CM Mohan Yadav has said, no effort will be spared to make Simhastha-2028 a historic and unforgettable event . Whether you're a devotee, a traveler, or an observer, the progress already made is impressive—and the journey to completion will be fascinating to watch. 🙏🚧



Frequently Asked Questions

Completed projects include the security audit identifying crowd-sensitive areas and CCTV locations, the head regulator and four shafts for the Kanh Closed Duct Diversion Project, and the upgrade of Shankarpur Substation from 20 MVA to 50 MVA. The bhoomi pujan for the Ujjain-Jaora Greenfield Corridor has also been completed.

As of June 2026, the head regulator and all four shafts for the tunnel section are complete. Tunnel excavation has progressed to 8.15 km out of 12 km (68%), and precast segments for 10.30 km of the 18.15 km cut-and-cover section have been prepared, with 4.50 km already laid.

The 29.15-kilometer ghat construction project worth ₹778 crore is ongoing, with the newly developed Triveni Ghat already established for review. Officials are working to ensure highest quality and adherence to timelines before Simhastha 2028.

The Shankarpur Substation has been upgraded from 20 MVA to 50 MVA capacity. The Jyotinagar 132kV substation is being continuously maintained. Chintaman (132kV) and Tajpur (400kV) substation expansions are still in progress. MPPTCL targets completing all power projects by March 2027.

The ₹5,017 crore, 98.73-kilometre corridor had its bhoomi pujan on July 11, 2026. It will connect Ujjain to the Delhi-Mumbai Expressway with seven flyovers, three rail overbridges, eight major bridges, and 430 culverts, with target completion by December 2027.

An estimated 40 crore devotees are expected to visit Ujjain during Simhastha 2028, making it the largest religious gathering in the world. The government is preparing facilities accordingly across multiple sectors.

Arrangements will allow around one lakh devotees per day to have darshan of Lord Mahakal. If more devotees arrive, the administration will provide accommodation and allow darshan the next day.

This ₹919.94 crore project prevents polluted water from the Kanh River from entering the Shipra River's major ghats and pilgrimage sites. A barrage on the Kanh River diverts polluted water through a closed duct system, discharging it 30.15 km downstream, ensuring clean water for holy dips.

Major road projects include the Ujjain-Indore six-lane highway (₹1,692 crore), Indore-Ujjain greenfield four-lane corridor (₹2,935 crore), Ujjain-Jaora four-lane (₹5,017 crore), plus 22 new bridges, five railway over-bridges, and 17 river bridges.

The Ujjain City Water Augmentation Scheme (₹1,133 crore) includes a 200 MLD water treatment plant, over 700 km of pipeline, 17 new overhead tanks, and nearly 49,000 new drinking water connections to serve the massive influx of pilgrims.

Development works worth more than ₹25,000 crore are progressing across multiple districts as part of Simhastha preparations, covering roads, ghats, power, water, parking, and temple infrastructure.

The upcoming Simhastha is scheduled to take place between March 27, 2028 and May 27, 2028. MPPTCL targets completing all power projects one year in advance, by March 2027.

About 60,000 police personnel will be deployed during Simhastha. Additional support may also come from other states. A security audit has identified crowd-sensitive areas, CCTV locations, and display centers.

A ₹30-crore master plan is revamping Khajrana Ganesh Temple with a two-storey zigzag darshan corridor allowing 5,000 pilgrims to complete darshan within 10 minutes. Phase 1 includes lowering the assembly hall floor and widening entry gates. Phase 2 includes a meditation centre, library, and emergency medical unit.