The 29km Shipra River Pathway: A Walkthrough of the ₹771 Crore Project
Chief Minister Dr. Mohan Yadav inspected the construction of the 29 km new ghats in Ujjain under Simhastha 2028 and directed authorities to ensure high-quality standards and timely completion.
The 29km Shipra River Pathway: A Walkthrough of the ₹771 Crore Project
As we move through 2026, the transformation of Ujjain into a global spiritual capital is no longer just a plan—it is a visible reality. The cornerstone of this metamorphosis is the 29.21-kilometer stretch of new ghats and pathways along the holy Shipra River.
In a recent high-level inspection, Chief Minister Dr. Mohan Yadav personally assessed the progress of this ₹771 crore (revised to approx. ₹864 crore including barrages) project, signaling that the "Green-Ujjain, Clean-Ujjain" vision for Simhastha 2028 is on a fast track to completion.
1. The Project Scope: A 29km Spiritual Corridor
The project is not merely about laying stone; it is an architectural feat designed to accommodate the 2 crore daily visitors expected during peak Shahi Snan days.
-
The Stretch: The pathway extends from the Shani Temple (Triveni Sangam) on the southern end to the Nagda Bypass on the north.
Trending Guides Now
Simhastha 2028 Latest Update: Disaster Mitra Training Begins in Ujjain
Government Doubles Powers of Ujjain Mayor and Commissioner Ahead of Simhastha 2028
Ujjain Simhastha 2028: ₹700 Crore Bypass Road Plan to Manage 30 Crore Pilgrims
Simhastha 2028 Ujjain Development Plan: What’s Changing Before the Kumbh
Ujjain Railway Station to Mahakaleshwar Temple Distance (2026 Guide)
Ujjain Simhastha 2028 Dates Announced: Full Shahi Snan & Event Timeline
Ujjain Simhastha Update: CM Mohan Yadav Reviews 2028 Works
Karkateshwar Mahadev: 22/84 Mahadev of Ujjain
-
Expansion: This project effectively triples the existing ghat capacity of Ujjain, ensuring that even at peak density, pilgrims have safe and structured access to the water.
-
The Material: To ensure a lifespan that lasts for decades of Simhasthas to come, the government is using Basalt and Red Stone, known for their durability and slip-resistance.
2. Chief Minister's 2026 Inspection Highlights
During his March 2026 visit, CM Dr. Mohan Yadav emphasized a shift from "Macro-planning" to "Ground-level Quality." His directives to the executing agencies (including Indore-based Falodi Construction) focused on three critical pillars:
-
Zero-Compromise Quality: Structural integrity must be capable of handling massive crowd pressure. The CM reviewed material samples and site management protocols to ensure the ghats are "future-proof."
-
Integrated Public Amenities: The project now mandates the integration of drinking water points, high-intensity lighting, and mobile-charging zones directly into the ghat architecture.
-
The "Nano-Management" Approach: Officials have been told to resolve bottlenecks through on-site feedback rather than paperwork, aiming for a strict completion deadline of June 2027.
3. Key Features of the New Riverfront
The 29km corridor is being divided into specialized zones to cater to different types of pilgrims:
| Feature | Specification / Detail |
| Entrance Gates | 15-meter wide entries every 500 meters to prevent bottlenecks. |
| Landing Platforms | 5-meter upper landing and 6-meter lower landing for safe movement. |
| Bathing Facilities | Specialized stepped ghats with safety railings and depth markers. |
| Specialized Zones | Dedicated ghat sections for the 13 Akharas and VIP movements. |
| Boat Transportation | Integration with the new Shipra Water Taxi (Triveni to Kaliyadeh Palace). |
4. Beyond the Ghats: The Ecological Mission
A riverfront is only as good as its river. Parallel to the ₹771 crore ghat project, the government is executing the ₹920 crore Kanh River Diversion.
-
The Goal: To ensure that the water in which devotees bathe is "Aachaman-worthy" (potable/pure).
-
The Tech: A 30km closed duct is being built to divert industrial and city waste away from the Shipra, ensuring a continuous flow of fresh water via the Narmada-Shipra Link.
5. Why This Matters for 2028
Simhastha 2028 is expected to attract nearly 15 crore visitors over one month. By transforming the riverfront into a structured, modern, yet culturally rooted corridor, Ujjain is setting a new global benchmark for religious event management.
The 29km pathway will act as the "main artery" of the Mela, connecting the Mahakal Lok Corridor with the satellite towns and transport hubs like the new Indore-Ujjain Metro stations.